Project Metrics
- EV testing stations
- 20ct
- DC fast charger
- 200kW
- Three-phase transformer
- 112kVA
- 240V three-phase panelboard
- 400A
Summary
20 EV testing stations and a 200 kW DC fast charger, powered by a new 112 kVA three-phase transformer and 400A panelboard, plus alarm, security access and cameras.
- Location
- Portland, OR
- Year
- 2024
- Client
- Op Connect
- Category
- Commercial